We have a number of exciting building and facilities works that have occurred and/or are occurring over the next few weeks (and also into the holidays).
If you have any questions throughout this time, please contact the office.
Building and Facilities update | Week 6 | Week 7 | Week 8 | Week 9 | Week 10 |
Saturday 25th August. Natasha Henry’s family member, connected the water tank for the new Kitchen Garden |
|||||
KAM Welding | Netball post closest to the new MPR has been fixed – again! | ||||
Armistead fencing | Majority of fencing works in the Kiss and Go and staff carpark completed Friday 24th August. Note: Gates still to be erected. |
From Monday 27th August:
|
|||
Votrix | Old MPR phone line now working | Phone line for New MPR and 1a/1b connected. Phone installation Wednesday 29th August. | |||
City Living
|
Saturday 25th August Year 3a and 3b railing for ramps have been cut and modified |
||||
Resolute | Saturday 25th August
Block (Admin) erected fencing per OHS |
Classroom #2 – painting No class access Wednesday 29th – Friday 31st August Note: no classes can be held in this space. |
|||
Classroom #1 – painting, office/conference room construction. Note: First Aid access through main corridor from breeze way (from front entrance emergency only). |
|||||
Block (Admin) eaves, fascias, gutters… |